Pine Street Project
9/11/2026
UPDATE ON THE UPCOMING PROJECT ON PINE STREET, FROM THE GAS STATIONS TO THE RAILROAD TRACKS:
Depending on the weather, work is scheduled to begin during the last week of September or the first week of October.
Here is an overview of the process and timeline:
Phase 1: Road Preparation & Base Stabilization (Approx. 2 days)
- We will begin by grinding the deepest swags to a depth of 8-10 inches, using base rock and a stabilization product to compact the base properly.
- Next, we will spread base rock over the entire route and grind to a depth of 6-7 inches while injecting the base stabilization product.
- A grader will shape the road while rollers simultaneously compact the surface.
Phase 2: Settling & Final Shaping (Approx. 2 days)
- The road will be open to traffic on the gravel surface for 24 to 48 hours to identify and correct any soft spots.
- We will then complete a final shaping and compaction of the road.
Phase 3: Surfacing (Approx. 2 days)
- We will apply a prime oil coat and allow it to cure for several hours.
- Once cured, we will apply the first layer of chip and seal using 1/2-inch rock.
- The following day, we will apply the second layer of chip and seal usiing 3/8-inch rock.
If all goes according to plan, the full project will take approximately six (6) days of active work and settling time.
TRAFFIC NOTICE:
During active work on site, the road will be closed to thru traffic. Access will be limited strictly to residents who have no alternative route to their homes.
Please contact City Hall with any further questions at 816-293-5601.